During the year 2024-25 the companys revenue is drastically reduced due to cash crunch for continuing the existing Projects and the Company has decided not to take any new order in BOP till the Banking problem persists. The Company is executing and closing the accepted projects and its progress was also hampered due to material and labour cost increase along with the cash flow. Companys inability to get additional working capital limits from its lenders/ banks and Banks classifying our loan as Non performing asset disrupted the Companys operations. Due to these developments, some of our contracts were either pre closed or terminated.
Project progress of Engineering and Construction Business
Unit I of the 3 x 660 MW Ghatampur thermal power project attained commercial operational in Dec 2024. Unit II and III are scheduled to be completed in the financial year 26. Physical progress achieved is 86% and financial progress is 82% as on 31st March25.
At the 1 x 800 MW NTTPS project of APGENCO, after the plant had gone into commercial operation in Dec 2023, the balance work relating to the Ash handling plant and other miscellaneous works have been completed. Works on the Coal handling plant is progressing well and are slated for completion by March 26. The project has achieved a progress of 85%.
For the NPCIL 2 x 1000 MW Light water Reactor project at Kudamkulam, we are executing the Electrical and C&I packages. On the Electrical package, the 220 KV GIS system is in an advanced stage of completion and the 220 KV GIS was recently taken into service. Work on the 400 KV GIS is progressing well. 80% of the Contract Value of Rs 430.0 Cr (including GST) has been delivered. An additional Rs 70.0 Cr order has been received in the current financial year. The job is slated for completion in Sept 2026. On the C&I package, supplies are happening in full swing and ~ 43% of the contract value of INR- 469.30 Cr have been delivered. Balance items are scheduled to be delivered by 31.03.2026.
We have completed the execution of Main Plant Electrical Systems Package Kakarapar Atomic Power Project (KAPP) 3 & 4 for Nuclear Power Corporation of India Limited. Final order value is Rs.284.90 crores including GST. The plant has been taken over by the customer and operational acceptance issued.
We are executing Main Plant Electrical Systems Package at NPCILs Rawatbatta Atomic Power Project (RAPP) Unit 7 & 8. Unit # 7 is completed and Operational acceptance obtained. Unit # 8 works are under progress. Total order value is 279.36 cr, out of which 97 % works are completed. Project is scheduled for completion by March 2026.
We are executing the 220kV Switchyard Extension project at Tarapur Maharashtra Site. The total order value is ~ Rs 90.0 Cr. More than 90% works are completed. Precommissioning works are under progress for completion in September 2025.
At the 2 x 600 MW, NTPCs TANDA Thermal Power Plant Stage - II, we are executing the Electrical Equipment Supply & Erection Package. Both unit # 1 and 2 are commissioned and operational. Balance Installation and Commissioning of Electrical auxiliaries are under progress. More than 95% of the job is completed.
Power Projects Division (PPD) - During the year 2024-25, the contract in North Chennai Thermal power project commissioned in March 2024 and no extension of order was undertaken.
Environmental Engineering Division (EED) - 10 MLD (Million Litres per Day) Tertiary treatment ultrafiltration (TTUF) plant in Nesapakkam was commissioned and subsequently, the contract has been terminated.
Electrical Project Division - For JUSNL Projects work was done upto August 2024 and discontinued thereafter.
Manufacturing Business (Product Business Division)
The capital goods segment, which manufacturers equipment for power, oil, gas and infrastructure industries, the Company made a turnover of Rs. 107 Crores during 202425.
INDUSTRY ANALYSIS & PROSPECTS IN DOMESTIC AND INTERNATIONAL MARKETS
The demand for power is increasing substantially. Despite the increase in renewable energy capacities, and despite the Renewable Purchase Obligation (RPO) set at 21%, thermal power has contributed more than 80% of the overall power consumption. The unprecedented power demand and the relative low contribution of renewable and nuclear power generation have brought to fore the urgent need to add significant capacity by way of new super critical & ultra-super critical thermal power projects with much lower heat rates. As per CEA, the annual Electrical Energy requirement will be 4 trillion units by FY 2035 while the current generation is only covering 35% of the requirement. This demand cannot be met alone with renewable sector. With state-run genco NTPC announcing that it is planning to be a 130 GW company in 2032, there is huge growth forecasted in thermal power sector which augurs well for the companys growth.
There is also huge scope in renovation & modernization of existing power plants, including replacement of old units with new power plants. In order to comply with the new emission standards, installation of Flue Gas Desulfurization units in existing power plants presents a new market segment to capitalize for the company.
The global energy crisis arising due to Russias invasion of Ukraine, has also forced countries worldwide to relook at coal based power plants. Denmark asked its biggest energy firm Rested to restart operations at three fossil fuel facilities to ensure energy security.
The Pradhan Mantri Gatishakti Bharat Master Plan for integrated infrastructure growth will offer robust growth potential in various sectors in the years to come. The National Infrastructure Pipeline, aimed at easier interconnectivity between road, rail, air and waterways to reduce travel time and improve industrial productivity, announced previously and re-emphasized again are envisaged to create multiplier effects on the economy. The flagship Jal Jeevan mission of GoI will see huge development under the rural and urban water supply infrastructure development in next couple of years. With our Civil Projects Division and Environmental Engineering Division, the company is in prime position to tap into this huge market.
The company is also exploring various business opportunities in Extra High Voltage (EHV) underground cabling projects, Traction Substation projects from Railways, Electrification packages for upcoming private projects, etc.
LOOKING INTO FUTURE AND STRATEGIC BUSINESS SHIFT
In the backdrop of challenges in thermal power sector in India and global markets as well, your Company initiated number of strategic initiatives. The Company identified critical need for shift from current business segments and identified some sectors as key drivers for growth in the medium term and diversify into adjacent business sectors to in which public and private investments. The companys proven and successful track record and competencies could be leveraged for growth in these emerging industrial, core and infrastructure sectors. These segments include: (i) Water and water treatment solutions
(ii) Electricity Transmission & Distribution (iii) Transport infrastructure viz.,Metro, Railways and Highways (iv) Civil construction; (v) Project exports and (vi) Oil & Gas and manufacture of equipment and systems for Indian industry and international markets. The Company would continueas a significant market player in thermal generation sector, being selective in order booking and would leverage its competencies in focusing and seeking orders from Nuclear power projects and power transmission activities. In capital goods / manufacturing businesses, the Company has taken measures to expand the geographical market reach in international markets by identifying key opportunities for expanding the product portfolio.
rinancial rerrormance (standalone)
SIGNIFICANT CHANGES IN FINANCIAL PERFORMANCE METRICS
The Operating margin for the year 2024-25 was negative due to lower turnover and higher cost of operations.
DETAILS OF ANY CHANGE IN RETURN ON NET WORTH AS COMPARED TO THE PREVIOUS FINANCIAL YEAR
During the year Net worth further decreased to -1321 crores from the previous year figure of -343 crores in 2023-24. The reduction in return on net worth is due to loss of 969.66 crores due to reduction in turnover, increase in cost, cancellation of orders due to classification of our accounts as Non Performing Assets by Banks.
STRENGTH AND OPPORTUNITIES
The company has after review of the current macro level developments and competition landscape planned foray into the Infrastructure, Highways Construction, Transmission. The experienced and competent manpower, proven project delivery of the Company is a rare strength. These rich credentials will enable qualification and successful breakthrough in all business segments. The strategic teams of experienced personnel formed recently are working on bids for these strategic segments.
INTERNAL CONTROL SYSTEMS AND AUDIT
As part of the audit system, the company has an in-house system with a works auditor. Experienced external firm of auditors carries out internal audit. The detailed audit plan is
well documented and audit scope is reviewed every year to include key processes that need improvements and address new compliance requirements. The detailed audit plan approved by the Audit Committee is rolled out at the beginning of each year. In addition, all payments to vendors are subjected to pre-audit by an external audit team.The statutory auditors carry out the required audit and compliance checks and review the control systems. The Chairman of Audit committee, key project personnel and the finance team review the audit reports of the internal auditors, pre auditors and in-house auditors in detail every quarter and a time bound action plan is initiated to address the key audit issues that need improvement and resolution. A summary of key audit observations, actiontaken to fix the gaps and the status is reviewed by the Audit Committee members in the quarterly audit committee meeting. The present internal control and audit systems are adequate.
RISK MANAGEMENT
The business of the Company encompasses design at office, manufacturing at factories and project sites, civil and mechanical construction, erection, and commissioning of equipments / packages. The company has a well-documented Standard Operating Systems and Procedures (SOSP). The SOSP mandates concerned officers of the company to review, identify and take timely steps to manage these risks on an ongoing basis. Delegation of Authority is reviewed each year to ensure that adequate controls are in place and required flexibility is available for effective operations at work site and that the commitments made to customers and vendors are met on time. Periodic review of procedural checks and balances are undertaken with a view to improve operationalcontrols and productivity matrix. An experienced team of contract specialists in the Company review all contractual documents with the customers and the vendors in detailto ensure that all risks associated with the terms of contract are fully understood,documented, and reviewed for ensuring effective implementation of the contracts.
HUMAN RESOURCE DEVELOPMENT
With the Pandemic threat fading away during the year 2024 - 25, there was a strong need to retain the critical manpower resources in the Company and rewarding them suitably. Accordingly, the Company carried out an exercise to identify the critical manpower across the Company and such critical employees were rewarded suitably.
During the year 2024 - 25 there were 9 employees who had completed more than 20 years service in our Organization. These employees were honored with long service awards during the Founders Day celebrations.
ENVIRONMENT, HEALTH AND SAFETY (EHS)
The Company treats EHS as its core need to carry on and grow the business on a sustained basis. The Company has adopted a structured approach towards implementation of EHS policy and plans to integrate EHS with critical operating processes to continually improve the environment in which the Company operates as well as the safety and health of all employees, workmen, general public and the society. The Company established EHS structure for developing, implementing, and improving EHS Management Systems. These systems are designed to imbibe and enhance safety culture
C INCKV7 T
and to mitigate high potential risks among the employees and contractors through appropriate interventionand guidance.
The Company took up many EHS initiatives viz., monitoring and control of air, noise and water pollution, fitness of all employees premedical screening, regular health awareness camps, blood donation, safety orientation to all new employees and contractors men before engaging at work, hazard identification and risk assessment for all critical activities, safety evaluation of contractors and adoption of EHS code of Practices by contractor, enhancement of behavior based safety programs, on spot motivation to safety conscious workers and recognition ofcreditable EHS performance. The EHS team strived to keep up good health of employees at offices, works and sites by strictly following the Standard Operating Procedures and guidelines issued by various Government and health authorities.
IIFL Customer Care Number
(Gold/NCD/NBFC/Insurance/NPS)
1860-267-3000 / 7039-050-000
IIFL Capital Services Support WhatsApp Number
+91 9892691696
IIFL Capital Services Limited - Stock Broker SEBI Regn. No: INZ000164132, PMS SEBI Regn. No: INP000002213,IA SEBI Regn. No: INA000000623, SEBI RA Regn. No: INH000000248, DP SEBI Reg. No. IN-DP-185-2016, BSE Enlistment Number (RA): 5016
ARN NO : 47791 (AMFI Registered Mutual Fund Distributor)
This Certificate Demonstrates That IIFL As An Organization Has Defined And Put In Place Best-Practice Information Security Processes.