The provisional certificate dated October 12, 2022 has been issued by the authority engineer for the length of 84.975 Km(Increased project length due to change of scope) and the project has been provisionally declared fit for entry into operation on April 04, 2022.
The project is “Development and upgradation of Bhawi-Pipar-Khimsar Highway (SH-86C) Length 83.225 Km in the state of Rajasthan on Engineering Procurement and Construction basis (EPC).
Accordingly, the HG Infra bid project cost is 85.41 crore and appointed date is June 20, 2018. The scheduled completion date was September 22, 2019.
On Friday, at around 11:01 AM, H.G. Infra Engineering Ltd is currently trading at Rs564.95 per share up by Rs5.45 or 0.97% from its previous closing of Rs559.50 per share on the BSE.
For feedback and suggestions, write to us at editorial@iifl.com
Related Tags

IIFL Customer Care Number
(Gold/NCD/NBFC/Insurance/NPS)
1860-267-3000 / 7039-050-000
IIFL Capital Services Support WhatsApp Number
+91 9892691696
IIFL Capital Services Limited - Stock Broker SEBI Regn. No: INZ000164132 (Member ID - NSE: 10975 BSE: 179 MCX: 55995 NCDEX: 01249), DP SEBI Reg. No. IN-DP-185-2016, PMS SEBI Regn. No: INP000002213, IA SEBI Regn. No: INA000000623, Merchant Banker SEBI Regn. No. INM000010940, RA SEBI Regn. No: INH000000248, BSE Enlistment Number (RA): 5016, AMFI-Registered Mutual Fund Distributor & SIF Distributor
ARN NO : 47791 (Date of initial registration – 17/02/2007; Current validity of ARN – 08/02/2027), PFRDA Reg. No. PoP 20092018, IRDAI Corporate Agent (Composite) : CA1099

This Certificate Demonstrates That IIFL As An Organization Has Defined And Put In Place Best-Practice Information Security Processes.