28 Sep 2022 , 02:37 PM
The completion certificate has been issued by the Independent Engineer and the project has been declared fit for entry into commercial operation on February 25, 2022.
The project was for six-laning and strengthening of new NH-248 A from existing km 11+682 to km 24+400 (design ch. 9+282 to km 22+000) under NHDP Phase -IV on Hybrid Annuity Mode in the state of Haryana.
The appointed date of the project was January 30, 2019, and was scheduled to be completed on July 28, 2021.
For feedback and suggestions, write to us at editorial@iifl.com
Related Tags
IIFL Customer Care Number
(Gold/NCD/NBFC/Insurance/NPS)
1860-267-3000 / 7039-050-000
IIFL Capital Services Support WhatsApp Number
+91 9892691696
IIFL Capital Services Limited - Stock Broker SEBI Regn. No: INZ000164132, PMS SEBI Regn. No: INP000002213,IA SEBI Regn. No: INA000000623, SEBI RA Regn. No: INH000000248
ARN NO : 47791 (AMFI Registered Mutual Fund Distributor)
This Certificate Demonstrates That IIFL As An Organization Has Defined And Put In Place Best-Practice Information Security Processes.